Skip to calculator
Concrete Free · No login

Concrete Calculator

Calculate concrete volume in cubic metres or yards for slabs, footings and columns. Includes bag count estimate. Free trade calculator for concrete. Covers AU and...

🧱
🎯

The footing excavation is done and the pump's booked for 7am. You need the cubic metres before you can confirm the order tonight.

Concrete Calculator
Concrete
Volume = L × W × D (+ 10% waste) Standard slab: 100mm deep. Footings typically 300mm+ deep. Always add 10% for spillage and uneven ground.
ℹ️ Results are estimates for planning purposes. Verify with current standards and a qualified professional.

1 What this calculator does

Calculates concrete volume in cubic metres (or cubic yards in imperial) for slabs, footings, columns and paths. Enter length, width and depth for any shape to get the volume plus a recommended number of pre-mix bags as a backup estimate.

2 Formula & professional reasoning

Volume (m³) = Length (m) × Width (m) × Depth (mm) ÷ 1000

Concrete is ordered by volume. Length and width give the plan area; depth is in mm in Australian practice (converted by dividing by 1000). Add 5–10% waste for over-pour, spills and uneven excavations. In imperial mode, feet × feet × inches ÷ 12 gives cubic feet, divided by 27 for cubic yards.

3 Worked examples

⚠️ Illustrative example only — not clinical or professional instruction.

Basic
Shed slab 4×3 m, 100 mm deep
Given: 4 m × 3 m × 100 mm
Working: 4 × 3 × 100 ÷ 1000 = 1.2 m³
Answer: 1.2 m³
💡 Add 10% waste → order 1.32 m³. Minimum truck load is typically 0.5 m³.
Standard
Driveway 12×3 m, 125 mm
Given: 12 × 3 × 125 ÷ 1000
Working: 12 × 3 × 125 ÷ 1000 = 4.5 m³
Answer: 4.5 m³
💡 Order 5 m³ including waste. Control joints every 3 m recommended.
Advanced
Strip footing 20 m run, 400 mm wide, 300 mm deep
Given: 20 × 0.4 × 0.3 = 2.4 m³
Working: 20 × 0.4 × 300 ÷ 1000
Answer: 2.4 m³
💡 Strip footings: run full length × cross-section area. Don't forget corner overlaps.

4 Sanity check

Residential slab
0.1–0.15 m³ per m² of floor area
100 mm slab = 0.1 m³/m²; 150 mm = 0.15 m³/m².
Minimum truck order
0.5 m³ most suppliers
Short loads carry a surcharge. Consider pre-mix bags for very small pours.
Waste allowance
Add 5–10%
10% for footings and uneven ground; 5% for clean formed slabs.
Pump vs chute
Over ~3 m from truck
Pump hire typically $400–$800. Worthwhile for complex or inaccessible pours.

5 Common errors

ErrorCauseConsequenceFix
Depth in wrong units Entering 100 m instead of 100 mm Result 1000× too large Australian concrete depth is always in millimetres — slab depth is 100 mm, not 0.1 m in this field
Ignoring waste Ordering exact volume Pour stops short — expensive emergency top-up Always add 5–10% to your calculated volume when ordering
Not accounting for reinforcement Assuming concrete fills 100% of volume Slight over-order (acceptable) Reo reduces volume by ~2–3% — negligible for ordering purposes
Confusing pour area with perimeter Footings measured as perimeter only Volume seriously underestimated Footings: multiply the full run length × cross-section (width × depth)